Putting Together a Brewery. Part 5
01.11.2012

Here is your fortnightly photo update on progress at our new brewery.
Today we brewed our first ever 100HL batch on our new Rolec brew-house. Everything went smoothly and the beer is now fermenting away in a shiny new fermentation tank.
In the new few days we have 3 bright beer tanks arriving as well as an additional 6 400HL fermentation tanks arriving early next week.

The whirlpool

Finally some action in the tanks brewhouse

Grabbing a wort sample

The beautiful first ever wort from our new brewhouse

Nikola adding the kettle hops

The case packer on our bottling line

Testing the labelling machine

Wallace cleaning the bottling machine

Foam jets get to work on our bottling machine

Our beer bottle chandalier
Comments
- Very impressive but so sorry you have left the Broch.Brewing smells over the beach added to our walks! braidsea05.11.2012
- nice chandelier. also love the hand painted details where you sample the wort and the logo on the tank window. lovely. heybrewtiful01.11.2012
- Well done guys this is just the start of the next stage for Brewdog B.W01.11.2012
- Sweet Chandelier! Ultimate Warrior01.11.2012
- Well done guys this is just the start of the next stage for Brewdog Wolf01.11.2012
- Aint no stopping us now.
World domination imminent !
Well done Team Dog !SashDog01.11.2012 - Congratulations team Brewdog. Bracken would be proud of you all. john.rolph01.11.2012
- perfect ! . congratz on your new house . cheers from Denmark kongeøl01.11.2012